EVALUASI KETERLAMBATAN PEMBANGUNAN JALAN PERKERASAN LENTUR (FLEXIBLE PAVEMENT)
Studi Kasus : Proyek Pembangunan Jalan
Rajawali Sakti dan Jalan Bima Kecamatan Tampan Pekanbaru
Muhammad Zikri 1), Hendra Taufik 2), Mardani Sebayang 2)
Mahasiswa Jurusan Teknik Sipil, Fakultas Teknik, Universitas Riau 1)
Dosen Jurusan Teknik Sipil, Fakultas Teknik, Universitas Riau 2)
Kampus Bina Widya Km. 12,5 Simpang Baru Pekanbaru, Kode Pos 28293
E-mail : Muhammad.zikri@student.unri.ac.id / hendra.taufik@lecturer.unri.ac.id / mardani.sebayang@lecturer.unri.ac.id
ABSTRACT
Construction project on Rajawali and Bima street in
Tampan district had delayed up to 33 days from the time of execution of project
should have been completed in 110 days. The evaluation done on critical path of
project had reveal that poor project management is the main cause of delay.
Project delay can be overcome by rescheduling and accelerating work settlement
on critical path. Some alternative method that such as addition of workers,
equipment and also shift system can be done to accelerate the period of
particular work settlement. The difference of each method revealed by the
comparison of overtime work productivity
calculation method, addition of workers and equipment productivity calculation
method, also shift system productivity calculation method. The result of analysis
had shown the cost of overtime work alternative method was Rp 134.465.669,63 addition
of workers and equipment alternative method was Rp 237.375.404,80 and
system shift alternative method was Rp 146.636.930,40. Also additional
cost for overwork productivity method was Rp 79.285.459,23 addition of workers
and equipment was Rp 185.815.046,26 and
shift system productivity method was Rp 192.746.756,20.
Keywords:alternative
method, productivity calculation method, overwork, addition of workers and
equipment, shift system.